Emergency Call-Out: Pumping Station Collapse Resolved Ahead of Major Event

Our team recently responded to an urgent issue at a dual foul pumping station servicing both an equestrian and veterinary centre.
๐ On arrival, we discovered a collapsed rising main pipework, causing the pumping station to fail just days before the centreโs scheduled open day.
To keep the site operational and avoid costly disruption, we swiftly installed a submersible hire pump with Heliflex hose, redirecting flow to a nearby discharge manhole in the car park.
โ Once repairs to the rising main were completed, the temporary system was removed and the station fully restored to service โ just in time for the weekendโs events.
Thanks to the team’s swift and effective response, the Wildlife Park and its associated facilities were able to remain fully operational, avoiding any disruption to services and preventing potential loss of revenue.
Our accredited work and commitment to high standards resulted in a successful outcome and highly satisfied clients.
๐ก By deploying our hire pump solution, the centre avoided the significant expense of tankering during the works.
Another successful outcome thanks to quick thinking, expertise, and teamwork ๐ทโโ๏ธ๐ช